Welcome to the Webberville Consolidated Drain Project

The purpose of this project is to improve the outdated storm sewer system in the Village of Webberville to alleviate flooding and protect nearby homes, businesses, and roads. This website will provide construction updates for the project including road closures, construction work areas, project schedule, project maps and pictures of ongoing construction.


The project began on May 18th on Chestnut St. between Elm Rd. and Howard St.

Ongoing: The contractor is working at the intersection of Chestnut St. and Howard St.

Upcoming: The contractor will begin moving work over to Monroe St. and Maple St. once they have finished this phase on Chestnut St. and Howard St.


Visit our construction updates page for more posts or click on the titles below to view posts in more detail.

June 2nd Update
The contractor is working at the intersection of Chestnut St. and Howard St. They will continue their work removing pavement and installing storm sewer structures …
May 29th Update
The contractor has continued their work along Chestnut St. They have removed the pavement at the intersection of Chestnut St. and Howard St. for the …